What does task time range help determine in a project?

  1. Budget overruns and cost implications

  2. If the project is ahead or behind schedule

  3. Resource allocation and personnel needs

  4. Quality control measures needed

The correct answer is: If the project is ahead or behind schedule

Task time range is essential for assessing the progress of a project over time. It provides insight into whether individual tasks are being completed as planned within their allocated timeframe. This framework is crucial for project managers to evaluate the current status of the project in relation to its schedule. By understanding the time range for each task, project managers can identify if a project is on track, ahead of schedule, or falling behind. This information plays a vital role in project management because staying within schedule is often as critical as adhering to budget constraints. Knowing where any delays occur helps in adjusting priorities or reallocating resources to ensure timely project completion. As such, the task time range directly correlates with the assessment of the project's pacing against planned deadlines.